Dept. of Trans. FINAL Serial No. Contract No. 20-324-09-16 09-380804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 09-MNO-395-12.6/35.4 ACNH-P395(279) Progress payment No. 004 Payment period ending: 08-28-20 AMERICAN PAVEMENT SYSTEMS INC 1012 11TH ST #1000 MODESTO CA 95354 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,023,550.88 0.00 2. a. Extra Work 25,532.28 0.00 b. Adustment Comp. -48,135.91 -52,904.15 3. Materials on Hand 4. Earned Subject to Retention 2,000,947.25 -52,904.15 5. Mobilization 6. Total Work Completed 2,000,947.25 7. Deductions 0.00 30,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,000,947.25 -22,904.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -22,904.15