Dept. of Trans. PROGRESS Serial No. Contract No. 20-358-13-16 09-380904 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 48% Location: Federal Project: 09-MNO-6-26.5/32.3 ACST-000C(516) 09-INY-178-42.9/48.6 Progress payment No. 003 Payment period ending: 12-20-20 QUALCON CONTRACTORS INC PO BOX 2889 MINDEN NV 89423 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,960,139.12 -7,110.00 2. a. Extra Work b. Adustment Comp. 74,899.36 74,899.36 3. Materials on Hand 4. Earned Subject to Retention 2,035,038.48 67,789.36 5. Mobilization 6. Total Work Completed 2,035,038.48 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,025,038.48 67,789.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 67,789.36