Dept. of Trans. FINAL Serial No. Contract No. 25-051-09-21 09-382104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 09-INY-168-17.5/17.8 NONE Progress payment No. 004 Payment period ending: 07-24-24 INTERSTATE CIVIL CONSTRUCTION PO BOX 2819 WRIGHTWOOD CA 92397 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 857,287.50 0.00 2. a. Extra Work 31,730.49 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 889,017.99 0.00 5. Mobilization 6. Total Work Completed 889,017.99 7. Deductions -201.00 20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 888,816.99 20,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 20,000.00