Dept. of Trans. PROGRESS Serial No. Contract No. 22-206-17-09 09-387804 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 82% Location: Federal Project: 09-INY-395-R6.4/R15.0 NONE Progress payment No. 003 Payment period ending: 07-20-22 ROAD & HIGHWAY BUILDERS LLC PO BOX 70846 RENO NV 89570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 816,742.00 5,796.20 2. a. Extra Work 62,633.12 62,633.12 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 879,375.12 68,429.32 5. Mobilization 6. Total Work Completed 879,375.12 7. Deductions -30,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 849,375.12 58,429.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 58,429.32