Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 22-312-09-33 09-393904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 09-MNO-395-53.1/54.7 NONE Progress payment No. 002 Payment period ending: 10-26-22 CORAL CONSTRUCTION COMPANY PO BOX 347 WILSONVILLE OR 97070 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 625,785.00 90,719.12 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 625,785.00 90,719.12 5. Mobilization 69,777.00 0.00 6. Total Work Completed 695,562.00 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 685,562.00 80,719.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 80,719.12