Dept. of Trans. PROGRESS Serial No. Contract No. 07-143-13-24 10-049954 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 55% 14% 10-AMA-49-R7.0/R11.0 Federal Project: NONE Progress payment No. 02 Payment period ending: 05-20-07 ODYSSEY LANDSCAPE COMPANY INC 800 W EIGHT MILE RD STOCKTON CA 95209 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 938,721.80 864,416.60 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 938,721.80 864,416.60 5. Mobilization 139,434.29 139,434.29 6. Total Work Completed 1,078,156.09 7. Deductions -86,441.66 -86,441.66 8. a.Contract Retentions -46,936.09 -39,505.57 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 944,778.34 877,903.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 877,903.66