Dept. of Trans. PROGRESS Serial No. Contract No. 08-171-10-22 10-0A1364 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 99% 10-MER-99-R28.7/R30.5 Federal Project: 10-MER-99-R33.1/R34.4 NONE Progress payment No. 14 Payment period ending: 06-13-08 FORSTER AND KROEGER LANDSCAPE MAINTENANCE INC 15 LIBRARY PLACE SAN ANSELMO CA 94960 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 235,475.00 7,805.00 2.a. Extra Work 49,767.72 16,687.72 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 285,242.72 24,492.72 5. Mobilization 6. Total Work Completed 285,242.72 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -14,262.14 -1,224.64 b. Unsatisfactory Prog. -1,224.63 -1,224.63 c. Reduction after 95% Comp. 9. Total pay to Contractor 259,755.95 22,043.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 22,043.45