Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 08-197-07-39 10-0A1364 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-MER-99-R28.7/R30.5 Federal Project: 10-MER-99-R33.1/R34.4 NONE Progress payment No. 15 Payment period ending: 06-27-08 FORSTER AND KROEGER LANDSCAPE MAINTENANCE INC 15 LIBRARY PLACE SAN ANSELMO CA 94960 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 239,000.00 3,525.00 2.a. Extra Work 62,540.65 12,772.93 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 301,540.65 16,297.93 5. Mobilization 6. Total Work Completed 301,540.65 7. Deductions -15,000.00 -5,000.00 8. a.Contract Retentions -14,262.14 0.00 b. Unsatisfactory Prog. 0.00 1,224.63 c. Reduction after 95% Comp. 14,262.14 14,262.14 9. Total pay to Contractor 286,540.65 26,784.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,784.70