Dept. of Trans. PROGRESS Serial No. Contract No. 04-359-10-14 10-0A5204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 31% 10-MER-99-23.8/R26.5 Federal Project: ACST-P099(475) PH-P099(475) Progress payment No. 04 Payment period ending: 12-20-04 TEICHERT CONSTRUCTION P O BOX 3367 TURLOCK CA 953813367 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 434,799.00 0.00 2.a. Extra Work 35,089.56 11,562.06 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 469,888.56 11,562.06 5. Mobilization 224,200.00 47,200.00 6. Total Work Completed 694,088.56 7. Deductions -69,053.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 625,035.56 58,762.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 58,762.06