Dept. of Trans. PROGRESS Serial No. Contract No. 05-082-12-44 10-0A7404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 8% 48% 10-SJ-120-9.4/16.6 Federal Project: ACNH-P120(44) Progress payment No. 03 Payment period ending: 03-20-05 TEICHERT CONSTRUCTION P O BOX 1118 STOCKTON CA 952011118 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 369,659.00 201,489.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -64,000.00 4. Earned Subject to Retention 369,659.00 137,489.00 5. Mobilization 72,500.00 72,500.00 6. Total Work Completed 442,159.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 442,159.00 209,989.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 209,989.00