Dept. of Trans. PROGRESS Serial No. Contract No. 13-023-08-30 10-0A8404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 60% 10-SJ-12-5.0/10.2 Federal Project: ACNH-000C(348) Progress payment No. 08 Payment period ending: 01-20-13 DE SILVA GATES CONTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,182,359.90 -7,310.00 2.a. Extra Work 186,718.34 97,063.63 b. Adjustment Comp. 3. Materials on Hand 0.00 -34,422.63 4. Earned Subject to Retention 5,369,078.24 55,331.00 5. Mobilization 959,000.00 0.00 6. Total Work Completed 6,328,078.24 7. Deductions -66,674.16 -22,438.41 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,261,404.08 32,892.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 32,892.59