Dept. of Trans. SEMI-FINAL Serial No. Contract No. 16-033-09-20 10-0C9004 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-STA-108-31.2/31.3 NONE Progress payment No. 008 Payment period ending: 08-25-15 DREAMBUILDER 1324 E LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 540,033.00 0.00 2. a. Extra Work 29,836.01 8,485.51 b. Adustment Comp. -2,792.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 567,077.01 8,485.51 5. Mobilization 6. Total Work Completed 567,077.01 7. Deductions -16,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 551,077.01 8,485.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,485.51