Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 16-008-13-49 10-0E6134 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-SJ-99-6.9/10.6 NONE Progress payment No. 035 Payment period ending: 12-15-15 BAY CITIES/MYERS JV PO BOX 6227 CONCORD, CA 94524-6227 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,131,969.63 97,174.90 2. a. Extra Work 1,873,875.38 37,468.01 b. Adustment Comp. -205,289.17 -11,856.77 3. Materials on Hand 4. Earned Subject to Retention 23,800,555.84 122,786.14 5. Mobilization 2,321,262.10 0.00 6. Total Work Completed 26,121,817.94 7. Deductions -31,884.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 26,089,933.94 122,786.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 122,786.14