Dept. of Trans. SEMI-FINAL Serial No. Contract No. 16-032-09-36 10-0E6134 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-SJ-99-6.9/10.6 NONE Progress payment No. 036 Payment period ending: 12-15-15 BAY CITIES/MYERS JV PO BOX 6227 CONCORD CA 94524-6227 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,190,746.55 58,776.93 2. a. Extra Work 1,875,769.42 1,894.04 b. Adustment Comp. -205,289.17 0.00 3. Materials on Hand 4. Earned Subject to Retention 23,861,226.80 60,670.97 5. Mobilization 2,321,262.10 0.00 6. Total Work Completed 26,182,488.90 7. Deductions -31,884.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 26,150,604.90 60,670.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 60,670.97