Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 11-305-13-15 10-0F1404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-ALP-5725 Federal Project: NONE Progress payment No. 09 Payment period ending: 10-20-11 ANDREW STURGEON CONSTRUCTION 8259 ALPINE AVENUE SACRAMENTO CA 95826 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 253,797.51 7,041.49 2.a. Extra Work 16,666.00 0.00 b. Adjustment Comp. 5,792.85 0.00 3. Materials on Hand 4. Earned Subject to Retention 276,256.36 7,041.49 5. Mobilization 6. Total Work Completed 276,256.36 7. Deductions -7,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 269,256.36 2,041.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,041.49