Dept. of Trans. PROGRESS Serial No. Contract No. 08-267-12-52 10-0F7304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 77% 10-STA-99-R15.0/R16.5 Federal Project: NONE Progress payment No. 10 Payment period ending: 09-20-08 ODYSSEY LANDSCAPING COMPANY INC 800 W EIGHT MILE RD STOCKTON CA 95209 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,309,998.84 10,832.78 2.a. Extra Work 88,529.35 0.00 b. Adjustment Comp. -1,153.53 -1,153.53 3. Materials on Hand 4. Earned Subject to Retention 1,397,374.66 9,679.25 5. Mobilization 157,000.00 0.00 6. Total Work Completed 1,554,374.66 7. Deductions -2,000.00 0.00 8. a.Contract Retentions -69,868.73 -483.96 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,482,505.93 9,195.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,195.29