Dept. of Trans. PROGRESS Serial No. Contract No. 09-328-11-01 10-0G3204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 55% 10-SJ-88-3.8/4.9 Federal Project: ACHS-P088(51) STPG-P088(51) Progress payment No. 05 Payment period ending: 11-20-09 KNIFE RIVER CONSTRUCTION 655 WEST CLAY STREET STOCKTON CA 952061722 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 905,402.64 160,487.07 2.a. Extra Work 68,398.47 39,718.16 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 973,801.11 200,205.23 5. Mobilization 24,000.00 0.00 6. Total Work Completed 997,801.11 7. Deductions -20,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 977,801.11 190,205.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 190,205.23