Dept. of Trans. PROGRESS Serial No. Contract No. 12-082-08-33 10-0G4704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 13% 10-SJ-5-28.5/35.6 Federal Project: ACIM-005(633) Progress payment No. 07 Payment period ending: 03-20-12 R & L BROSAMER INC 1777 OAKLAND BLVD SUITE 300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,399,217.85 1,878,448.90 2.a. Extra Work 413,801.40 40,471.48 b. Adjustment Comp. 3. Materials on Hand 396,244.80 -9,625.55 4. Earned Subject to Retention 11,209,264.05 1,909,294.83 5. Mobilization 6,000,000.00 0.00 6. Total Work Completed 16,813,019.25 7. Deductions -49,628.00 -13,058.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,159,636.05 1,896,236.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,896,236.83