Dept. of Trans. PROGRESS Serial No. Contract No. 16-173-10-46 10-0G4704 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 99% Location: Federal Project: 10-SJ-5-28.5/35.6 ACIM-005(633) Progress payment No. 063 Payment period ending: 06-20-16 R & L BROSAMER INC 1777 OAKLAND BLVD #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 72,407,395.22 396,425.77 2. a. Extra Work 8,127,067.61 329,383.29 b. Adustment Comp. 804,125.60 13,573.32 3. Materials on Hand 33,558.61 14,022.45 4. Earned Subject to Retention 81,372,147.04 753,404.83 5. Mobilization 8,000,000.00 0.00 6. Total Work Completed 89,338,588.43 7. Deductions -55,497.25 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 89,316,649.79 753,404.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 753,404.83