Dept. of Trans. PROGRESS Serial No. Contract No. 16-299-12-56 10-0G4704 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 99% Location: Federal Project: 10-SJ-5-28.5/35.6 ACIM-005(633) Progress payment No. 067 Payment period ending: 10-20-16 R & L BROSAMER INC 1390 WILLOW PASS RD #950 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 74,498,168.07 154,389.30 2. a. Extra Work 8,922,700.18 115,088.83 b. Adustment Comp. 806,795.03 -50,362.32 3. Materials on Hand 0.00 -16,954.13 4. Earned Subject to Retention 84,227,663.28 202,161.68 5. Mobilization 8,000,000.00 0.00 6. Total Work Completed 92,227,663.28 7. Deductions -75,497.25 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 92,152,166.03 192,161.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 192,161.68