Dept. of Trans. PROGRESS Serial No. Contract No. 17-023-14-28 10-0G4704 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 100% Location: Federal Project: 10-SJ-5-28.5/35.6 ACIM-005(633) Progress payment No. 070 Payment period ending: 01-20-17 R & L BROSAMER INC 1390 WILLOW PASS RD #950 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 74,754,267.71 53,198.20 2. a. Extra Work 9,137,008.74 6,558.76 b. Adustment Comp. 806,795.03 0.00 3. Materials on Hand 4. Earned Subject to Retention 84,698,071.48 59,756.96 5. Mobilization 8,000,000.00 0.00 6. Total Work Completed 92,698,071.48 7. Deductions -82,497.25 43,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 92,615,574.23 102,756.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 102,756.96