Dept. of Trans. SEMI-FINAL Serial No. Contract No. 10-259-08-06 10-0G7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-STA-33-0.5/14.5 Federal Project: SARR-S033(69) A-S033(69) Progress payment No. 06 Payment period ending: 08-13-10 KNIFE RIVER CONSTRUCTION P O BOX 6099 STOCKTON CA 952060099 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,190,242.22 0.00 2.a. Extra Work 61,018.81 33,749.92 b. Adjustment Comp. 27,294.16 -4,000.00 3. Materials on Hand 4. Earned Subject to Retention 1,278,555.19 29,749.92 5. Mobilization 34,000.00 0.00 6. Total Work Completed 1,312,555.19 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,307,555.19 29,749.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 29,749.92