Dept. of Trans. PROGRESS Serial No. Contract No. 15-324-11-55 10-0G8004 PROGRESS PAYMENT VOUCHER %complete: %time: 67% 44% Location: Federal Project: 10-SJ-12-0.1/R4.4 NH-P012(112) Progress payment No. 022 Payment period ending: 11-20-15 OC JONES & SONS, INC 1520 FOURTH STREET BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,488,155.21 310,224.25 2. a. Extra Work 3,077,176.74 2,456.26 b. Adustment Comp. 324,832.50 0.00 3. Materials on Hand 1,072,313.00 0.00 4. Earned Subject to Retention 21,962,477.45 312,680.51 5. Mobilization 705,000.00 0.00 6. Total Work Completed 21,595,164.45 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,665,477.45 312,680.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 312,680.51