Dept. of Trans. PROGRESS Serial No. Contract No. 08-142-10-19 10-0H3804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 27% 24% 10-CAL-12-14.0/14.5 Federal Project: NONE Progress payment No. 01 Payment period ending: 05-20-08 ON GRADE CONTRACTING P O BOX 159 JAMESTOWN CA 95327 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 97,249.75 97,249.75 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 97,249.75 97,249.75 5. Mobilization 5,985.00 5,985.00 6. Total Work Completed 103,234.75 7. Deductions 8. a.Contract Retentions -7,574.96 -7,574.96 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 95,659.79 95,659.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 95,659.79