Dept. of Trans. PROGRESS Serial No. Contract No. 06-235-10-56 10-0H5204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 25% 10-SJ-99-16.7/ .0 Federal Project: NONE Progress payment No. 02 Payment period ending: 08-20-06 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 02238 Total Estimate This Estimate 1. Contract Itms Without Mobil. 208,422.13 165,571.13 2.a. Extra Work 492.87 492.87 b. Adjustment Comp. 3. Materials on Hand 0.00 -4,567.50 4. Earned Subject to Retention 208,915.00 161,496.50 5. Mobilization 96,000.00 96,000.00 6. Total Work Completed 304,915.00 7. Deductions 8. a.Contract Retentions -20,891.50 -16,149.65 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 284,023.50 241,346.85 10. Reduction Amt to Escrow 11. Payment to Escrow 20,890.00 12. Net Pymt. this Estimate 241,346.85