Dept. of Trans. PROGRESS Serial No. Contract No. 07-143-10-55 10-0H5204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 83% 10-SJ-99-16.7/ .0 Federal Project: NONE Progress payment No. 11 Payment period ending: 05-20-07 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 02238 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,227,260.72 19,523.28 2.a. Extra Work 91,887.72 9,833.85 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,319,148.44 29,357.13 5. Mobilization 128,000.00 0.00 6. Total Work Completed 1,447,148.44 7. Deductions 8. a.Contract Retentions -65,957.42 -1,467.85 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,381,191.02 27,889.28 10. Reduction Amt to Escrow 11. Payment to Escrow 65,950.00 12. Net Pymt. this Estimate 27,889.28