Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-224-10-23 10-0J8104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-MER-140-36.5/ .0 Federal Project: NONE Progress payment No. 06 Payment period ending: 07-15-09 TEICHERT CONSTRUCTION P O BOX 3367 TURLOCK CA 95381 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 317,516.20 0.00 2.a. Extra Work 19,453.28 0.00 b. Adjustment Comp. 29,328.76 0.00 3. Materials on Hand 4. Earned Subject to Retention 366,298.24 0.00 5. Mobilization 39,000.00 0.00 6. Total Work Completed 405,298.24 7. Deductions -5,000.00 5,000.00 8. a.Contract Retentions -16,646.40 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 16,646.40 0.00 9. Total pay to Contractor 400,298.24 5,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,000.00