Dept. of Trans. PROGRESS Serial No. Contract No. 12-205-13-22 10-0K0204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 81% 10-MER-99-15.8/17.3 Federal Project: SARR-P099(521) A-P099(521) Progress payment No. 31 Payment period ending: 07-20-12 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,780,283.47 865,164.29 2.a. Extra Work 167,791.66 22,203.53 b. Adjustment Comp. 1,844,629.62 58,269.28 3. Materials on Hand 243,673.47 -26,715.56 4. Earned Subject to Retention 12,036,378.22 918,921.54 5. Mobilization 1,885,000.00 0.00 6. Total Work Completed 13,677,704.75 7. Deductions -12,940.72 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,908,437.50 908,921.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 908,921.54