Dept. of Trans. PROGRESS Serial No. Contract No. 13-165-12-56 10-0K0204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 99% 10-MER-99-15.8/17.3 Federal Project: SARR-P099(521) A-P099(521) Progress payment No. 45 Payment period ending: 06-20-13 RGW CONSTRUCTION INC 550 GREENVILLE ROAD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,291,511.14 695,719.33 2.a. Extra Work 806,746.59 104,030.85 b. Adjustment Comp. 2,126,082.12 44,767.72 3. Materials on Hand 27,572.20 0.00 4. Earned Subject to Retention 18,251,912.05 844,517.90 5. Mobilization 1,885,000.00 0.00 6. Total Work Completed 20,109,339.85 7. Deductions -2,940.72 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 20,133,971.33 844,517.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 844,517.90