Dept. of Trans. PROGRESS Serial No. Contract No. 15-021-13-19 10-0K0214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 39% 10% 10-MER-99-15.8/17.3 Federal Project: NONE Progress payment No. 02 Payment period ending: 01-20-15 WABO LANDSCAPE & CONSTRUCTION, INC. 726 ALFRED NOBEL DRIVE HERCULES CA 94547 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 157,996.50 142,335.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 31,143.80 0.00 4. Earned Subject to Retention 189,140.30 142,335.50 5. Mobilization 57,950.00 27,450.00 6. Total Work Completed 215,946.50 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 247,090.30 169,785.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 169,785.50