Dept. of Trans. FINAL Serial No. Contract No. 05-215-14-28 10-0K5204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-SJ-5-28.2/29.8 Federal Project: NONE Progress payment No. 04 Payment period ending: 05-05-05 DEBRUIN CONSTRUCTION INC P O BOX 1355 FRENCH CAMP CA 95231 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 337,697.83 0.00 2.a. Extra Work 1,612.04 1,612.04 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 339,309.87 1,612.04 5. Mobilization 6. Total Work Completed 339,309.87 7. Deductions 0.00 10,000.00 8. a.Contract Retentions -7,553.50 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 7,553.50 0.00 9. Total pay to Contractor 339,309.87 11,612.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,612.04