Dept. of Trans. PROGRESS Serial No. Contract No. 06-297-08-53 10-0K5604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 93% 10-SJ-99-35.6/36.3 Federal Project: NONE Progress payment No. 01 Payment period ending: 10-20-06 GEORGE REED INC P O BOX 1630 LODI CA 95241 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 455,911.88 455,911.88 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 455,911.88 455,911.88 5. Mobilization 6. Total Work Completed 455,911.88 7. Deductions 8. a.Contract Retentions -22,795.59 -22,795.59 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 433,116.29 433,116.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 433,116.29