Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 11-355-10-57 10-0K7004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-STA-99-R21.9/R22.3 Federal Project: NONE Progress payment No. 18 Payment period ending: 12-07-11 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 648,766.33 1,657.55 2.a. Extra Work 76,241.72 3,828.80 b. Adjustment Comp. -1,910.20 0.00 3. Materials on Hand 4. Earned Subject to Retention 723,097.85 5,486.35 5. Mobilization 39,000.00 0.00 6. Total Work Completed 762,097.85 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 757,097.85 486.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 486.35