Dept. of Trans. PROGRESS Serial No. Contract No. 20-238-08-09 10-0L0204 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 68% Location: Federal Project: 10-SJ-99-0.0/0.7 B1NH-P099(634) 10-STA-99-R24.4/R24.8 Progress payment No. 018 Payment period ending: 08-20-20 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,478,313.15 539,220.00 2. a. Extra Work 967,115.37 -6,133.80 b. Adustment Comp. 3. Materials on Hand 236,609.00 0.00 4. Earned Subject to Retention 3,682,037.52 533,086.20 5. Mobilization 694,000.00 34,700.00 6. Total Work Completed 4,139,428.52 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,366,037.52 567,786.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 567,786.20