Dept. of Trans. PROGRESS Serial No. Contract No. 20-266-14-34 10-0L0204 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 72% Location: Federal Project: 10-SJ-99-0.0/0.7 B1NH-P099(634) 10-STA-99-R24.4/R24.8 Progress payment No. 019 Payment period ending: 09-20-20 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,147,140.05 668,826.90 2. a. Extra Work 964,889.87 -2,225.50 b. Adustment Comp. 3. Materials on Hand 47,477.00 -189,132.00 4. Earned Subject to Retention 4,159,506.92 477,469.40 5. Mobilization 694,000.00 0.00 6. Total Work Completed 4,806,029.92 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,843,506.92 477,469.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 477,469.40