Dept. of Trans. PROGRESS Serial No. Contract No. 08-171-10-22 10-0L0504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 72% 10-MER-33-16.4/16.4 Federal Project: NONE Progress payment No. 03 Payment period ending: 06-20-08 TEICHERT CONSTRUCTION P O BOX 3367 TURLOCK CA 95381 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 221,192.60 41,740.00 2.a. Extra Work 1,942.76 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 223,135.36 41,740.00 5. Mobilization 26,000.00 0.00 6. Total Work Completed 249,135.36 7. Deductions -4,500.00 0.00 8. a.Contract Retentions -11,156.77 -2,087.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 233,478.59 39,653.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 39,653.00