Dept. of Trans. PROGRESS Serial No. Contract No. 10-260-08-30 10-0L6304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 10-SJ-99-0.0/1.7 Federal Project: 10-STA-99-R24.3/R24.8 HSNH-P099(523) G-P099(523) Progress payment No. 06 Payment period ending: 09-17-10 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 693,557.18 78,931.00 2.a. Extra Work 16,451.13 14,340.78 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 710,008.31 93,271.78 5. Mobilization 281,250.00 0.00 6. Total Work Completed 991,258.31 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 986,258.31 93,271.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 93,271.78