Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-139-08-40 10-0L6404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-STA-99-R10.3/R12.0 Federal Project: OTS Progress payment No. 14 Payment period ending: 04-21-09 TEICHERT CONSTRUCTION P O BOX 3367 TURLOCK CA 95381 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,428,868.10 2,224.50 2.a. Extra Work 1,078,848.00 0.00 b. Adjustment Comp. 26,690.61 -2,045.08 3. Materials on Hand 4. Earned Subject to Retention 2,534,406.71 179.42 5. Mobilization 239,000.00 0.00 6. Total Work Completed 2,773,406.71 7. Deductions -15,704.50 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,757,702.21 179.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 179.42