Dept. of Trans. PROGRESS Serial No. Contract No. 07-206-13-04 10-0L7104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 56% 14% 10-MER-152-R9.8/10.0 Federal Project: NONE Progress payment No. 01 Payment period ending: 07-20-07 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 157,134.00 157,134.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 157,134.00 157,134.00 5. Mobilization 28,500.00 28,500.00 6. Total Work Completed 185,634.00 7. Deductions 8. a.Contract Retentions -7,856.70 -7,856.70 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 177,777.30 177,777.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 177,777.30