Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-258-13-46 10-0L7204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-STA-108-30.5/31.6 Federal Project: ACHS-P108(46) STPG-P108(46) Progress payment No. 04 Payment period ending: 08-14-09 GEORGE REED INC P O BOX 4760 MODESTO CA 95352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 694,998.49 4,496.45 2.a. Extra Work 53,683.05 46,874.47 b. Adjustment Comp. -36,452.30 -36,452.30 3. Materials on Hand 4. Earned Subject to Retention 712,229.24 14,918.62 5. Mobilization 6. Total Work Completed 712,229.24 7. Deductions -10,000.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 702,229.24 24,918.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,918.62