Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 09-335-13-24 10-0M2404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-TUO-108-64.5/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 11-12-09 R A NEMETZ CONSTRUCTION CO INC P O BOX 32 WILTON CA 95693 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 229,728.50 44,352.25 2.a. Extra Work 189,390.98 10,456.06 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 419,119.48 54,808.31 5. Mobilization 25,000.00 0.00 6. Total Work Completed 444,119.48 7. Deductions -15,000.00 -15,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 429,119.48 39,808.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 39,808.31