Dept. of Trans. FINAL Serial No. Contract No. 10-035-10-00 10-0M2404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-TUO-108-64.5/ .0 Federal Project: NONE Progress payment No. 05 Payment period ending: 11-12-09 R A NEMETZ CONSTRUCTION CO INC P O BOX 32 WILTON CA 95693 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 257,668.50 12,500.00 2.a. Extra Work 190,905.98 1,515.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 448,574.48 14,015.00 5. Mobilization 25,000.00 0.00 6. Total Work Completed 473,574.48 7. Deductions 0.00 5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 473,574.48 19,015.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 19,015.00