Dept. of Trans. PROGRESS Serial No. Contract No. 05-325-10-25 10-0M2704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 96% 10-SJ-5-0.3/R13.8 Federal Project: NONE Progress payment No. 05 Payment period ending: 11-20-05 WINDSOR FUEL CO P O BOX 38 WINDSOR CA 954920038 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,844,312.11 303,248.55 2.a. Extra Work 35,000.00 0.00 b. Adjustment Comp. -96,591.65 -96,591.65 3. Materials on Hand 4. Earned Subject to Retention 1,782,720.46 206,656.90 5. Mobilization 40,000.00 0.00 6. Total Work Completed 1,822,720.46 7. Deductions -28,500.00 -10,000.00 8. a.Contract Retentions -89,136.02 -10,332.84 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,705,084.44 186,324.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 186,324.06