Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-241-08-06 10-0M2704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-SJ-5-0.3/R13.8 Federal Project: NONE Progress payment No. 09 Payment period ending: 08-18-06 WINDSOR FUEL CO P O BOX 38 WINDSOR CA 954920038 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,845,062.11 200.00 2.a. Extra Work 35,000.00 0.00 b. Adjustment Comp. -96,591.65 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,783,470.46 200.00 5. Mobilization 40,000.00 0.00 6. Total Work Completed 1,823,470.46 7. Deductions -10,000.00 18,500.00 8. a.Contract Retentions -89,163.52 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 89,163.52 28,601.38 9. Total pay to Contractor 1,813,470.46 47,301.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 47,301.38