Dept. of Trans. FINAL Serial No. Contract No. 07-130-13-42 10-0M3204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-SJ-132-L0.6/2.2 Federal Project: 10-SJ-132-4.2/5.8 NONE Progress payment No. 05 Payment period ending: 10-23-06 PROFESSIONAL CONSTRUCTION SERVICES 164 BELLE AVE PLEASANT HILL CA 94523 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 626,702.03 0.00 2.a. Extra Work 10,257.51 8,757.51 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 636,959.54 8,757.51 5. Mobilization 6. Total Work Completed 636,959.54 7. Deductions 0.00 10,000.00 8. a.Contract Retentions -30,031.41 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 30,031.41 0.00 9. Total pay to Contractor 636,959.54 18,757.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,757.51