Dept. of Trans. SEMI-FINAL Serial No. Contract No. 08-352-09-53 10-0M4304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-TUO-49-12.6/16.5 Federal Project: NONE Progress payment No. 04 Payment period ending: 11-19-08 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 655,667.20 0.00 2.a. Extra Work 30,115.55 2,115.55 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 685,782.75 2,115.55 5. Mobilization 6. Total Work Completed 685,782.75 7. Deductions -10,801.52 0.00 8. a.Contract Retentions -31,503.47 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 31,503.47 0.00 9. Total pay to Contractor 674,981.23 2,115.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,115.55