Dept. of Trans. PROGRESS Serial No. Contract No. 14-052-09-39 10-0M7804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 24% 30% 10-SJ-5-25.1/28.6 Federal Project: ACIM-056(338) 470(338) Progress payment No. 10 Payment period ending: 02-20-14 DESILVA GATES CONSTRUCTION LP P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,553,122.02 176,139.00 2.a. Extra Work 387,997.12 108,725.12 b. Adjustment Comp. 66,384.85 0.00 3. Materials on Hand 668,830.39 20,565.05 4. Earned Subject to Retention 7,676,334.38 305,429.17 5. Mobilization 3,029,250.00 0.00 6. Total Work Completed 10,036,753.99 7. Deductions -22,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,683,584.38 305,429.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 305,429.17