Dept. of Trans. PROGRESS Serial No. Contract No. 15-082-08-16 10-0M7804 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 64% Location: Federal Project: 10-SJ-5-25.1/28.6 ACIM-056(338) 470(338) Progress payment No. 024 Payment period ending: 03-20-15 DESILVA GATES CONSTRUCTION LP P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,299,794.23 1,327,452.58 2. a. Extra Work 3,196,694.01 114,485.63 b. Adustment Comp. 1,870,918.72 232,249.75 3. Materials on Hand 25,026.34 0.00 4. Earned Subject to Retention 26,392,433.30 1,674,187.96 5. Mobilization 4,039,000.00 0.00 6. Total Work Completed 30,406,406.96 7. Deductions -65,681.54 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 30,365,751.76 1,664,187.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,664,187.96