Dept. of Trans. PROGRESS Serial No. Contract No. 15-295-09-15 10-0M7804 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 88% Location: Federal Project: 10-SJ-5-25.1/28.6 ACIM-056(338) 470(338) Progress payment No. 032 Payment period ending: 10-20-15 DESILVA GATES CONSTRUCTION LP P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,886,073.38 1,160,896.18 2. a. Extra Work 4,737,820.92 414,464.50 b. Adustment Comp. 2,218,419.67 -126,009.38 3. Materials on Hand 35,586.19 0.00 4. Earned Subject to Retention 35,877,900.16 1,449,351.30 5. Mobilization 4,039,000.00 0.00 6. Total Work Completed 39,881,313.97 7. Deductions -115,747.90 32,075.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 39,801,152.26 1,481,426.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,481,426.30