Dept. of Trans. PROGRESS Serial No. Contract No. 16-145-09-10 10-0M7804 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 74% Location: Federal Project: 10-SJ-5-25.1/28.6 ACIM-056(338) 470(338) Progress payment No. 040 Payment period ending: 05-20-16 DESILVA GATES CONSTRUCTION LP PO BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 29,786,361.18 215,448.53 2. a. Extra Work 5,075,197.60 2,646.76 b. Adustment Comp. 2,922,941.26 507,663.47 3. Materials on Hand 35,586.19 -0.02 4. Earned Subject to Retention 37,820,086.23 725,758.74 5. Mobilization 4,039,000.00 0.00 6. Total Work Completed 41,823,500.04 7. Deductions -120,747.90 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 41,738,338.33 730,758.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 730,758.74